title subtitle author email summary header-includes
Remodel Phase 2 (Bathroom)
Richland Prefab 2BR
John D. Fisher
jdfenw@gmail.com
Proposed Phase 2 changes to the Bathroom. Collect plans for Phase 2 to be completed separatetly from the Kitchen, Living Room and Bedrooms.
```{=html} <link rel="stylesheet" type="text/css" media="print" href="print.css" /> ```

Bathroom Phase 2

  • Shower cabinet should be clear doors and cultured marble on walls and pan.
    • Doors should slide with top rail close to ceiling to maximize headroom. Both doors should move to allow access to utility faucet See Bathroom Cabinets and Fixtures for related details.
    • We like cultured marble: Orchard Mexican Sand, light mink, country gray and white.
  • Finish and paint bathroom. Sherwin Williams 7002 Downy Enamel, Emerald Interior Acrylic Latex would match the rest of the house well (we're using Eggshell in the other rooms).

Bathroom Walls and Floor Phase 2

  • Insulate the floor and walls.
  • Replace bathroom walls with drywall or recommend better material. We prefer a smooth surface for easy cleaning.
  • Replace tile floor with TAS Bourbon Street Applewood LOLG1039. Use leftover flooring from Phase 1.
  • Replace window. Current window has draining issues due to freezing and algae accumulation. Options to estimate:
    • A fixed bottom, vertical sash that drains into the shower.
    • Sealed privacy window.
    • Glass brick.

Bathroom Electrical Phase 2

  • Replace exhaust fan with a quiet, high flow model, similar to BR#2. Fan should maximize headroom and use LED lighting.
  • Separate light and fan switch into two switches.
  • Add recessed lights:
    • Over vanity
    • Over shower, if needed.
    • Lights may share one switch.
  • Retain duplex outlet, adjacent to vanity for hair dryer, curling iron etc.
  • Add 2x duplex outlets for above toilet shelves.

Bathroom Cabinets and Fixtures Phase 2

  1. Remove old sink and cabinet.

  2. Retain mirror cabinet:

    GODMORGON Mirror cabinet with 2 doors

    Article Number: 102.189.99 Size: 23-5/8 x 5-1/2 x 37-3/4 inches. Already purchased.

  3. Retain rack behind toilet.

  4. Retain towel rack near current location.

  5. New sink faucet: DALSKÄR Bath faucet with strainer, chrome plated

    Article Number: 202.812.97 Height: 7-1/8 inches.

  6. New sink: IKEA

    GODMORGON / ODENSVIK Sink cabinet with 2 drawers, brown stained ash effect

    Article Number: 093.051.86 Size 24-3/4 x 19-1/4 x 25 1/4 inches.

    1. Add GODMORGON legs since wall-mount is not likely to be strong enough. GODMORGON Leg, round/stainless steel Article Number: 303.498.38 Min. Height: 5 7/8 " Max. Height: 9 7/8 "
  7. Retain handheld shower and filter and add a utility faucet.

    1. Surface mounted utility faucet that can be moved out of the way, when the shower is in use. The water supply should tee, so a shower diverter is not needed.
    2. Whitehaus WHFS9814-08-C Heavy Duty wall mount utility faucet with an extended swivel spout and lever handles - Polished Chrome
    3. Utility faucet should be high enough to fill a commercial mop bucket (~24 inches).
    4. The shower control should be temperature regulated, e.g.:
  8. Toilet

    1. Havenstone 1-piece 1.1/1.6 GPF Dual Flush Elongated Toilet in White Seat Included Internet #317905474 Model #GBTO203 Store SKU #1006711441
    2. Retain tee-valve and spray hose.